Forest Park's power line plan is back after a hearings officer approved PGE's revision
The PDXtoday team
If you hike Forest Park, this one's back. A city hearings officer approved Portland General Electric's revised plan on Friday, a year after the City Council rejected the first version. The Harborton Reliability Project would rewire a 1970s transmission line and add a second one inside PGE's existing right of way through the 5,200-acre park. PGE says it's needed to avoid outages in North and Northwest Portland.
The ruling allows PGE to remove 375 living trees in Forest Park
- 375
- living trees the ruling allows removing, plus 18 dead ones
- $5.5 million
- for mitigation in or next to the park
- 4.7 acres
- of natural resource land disturbed
Sources: The Oregon Journal, OregonLive.com
Hearings officer Marisha Childs required that a large share of the money be spent in the part of the park where construction will happen, The Oregon Journal reports. Some environmental groups call the mediation agreement behind the plan a “backroom deal.” Childs wrote that such arguments fall “beyond the scope of the Hearings Officer.”
- Appeal deadline: Dec. 4, to the City Council
- Forest Park Conservancy will likely appeal, board member Carole Hardy said
- PGE must complete wildlife surveys before construction begins
- Timing limits will protect amphibians during the work
PGE's approval can be appealed to the City Council by Dec. 4
- June 2025A hearings officer approves PGE's original plan.
- JulyThe city and PGE reach a mediation agreement with $5.5 million for mitigation.
- Oct. 14The city holds a public hearing on PGE's revised proposal.
- Nov. 4The hearing record closes.
- Nov. 20Hearings officer Marisha Childs approves the revised proposal.
- Dec. 4Deadline to appeal the approval to the City Council.